Asbestos Case Study for Property Refurbishment

Asbestos Case Study for Property Refurbishment

A refurbishment budget can change materially when hidden asbestos-containing materials are found after work has started. This asbestos case study follows a typical UK scenario: a landlord preparing a 1970s flat for re-letting, where an appropriately scoped survey identified risks that were not visible during a routine viewing.

The outcome was not simply an asbestos register. It was a practical route to complete the works safely, avoid uncontrolled disturbance and make informed decisions about programme, contractor competence and cost.

The property and the planned works

The property was a two-bedroom leasehold flat within a purpose-built block constructed in the mid-1970s. The landlord had recently taken ownership and intended to carry out a full internal refresh before letting it: removal of old floor finishes, replacement of the kitchen and bathroom, electrical upgrades, new heating pipework, redecoration and minor alterations to fitted cupboards.

At first glance, the flat appeared straightforward. There was no obvious damage to ceilings or wall linings, and previous decorative work had concealed much of the original construction. However, the building age and scope of planned disturbance meant asbestos could not be treated as a theoretical concern.

This distinction matters. A management asbestos survey is intended to help manage asbestos-containing materials that may be disturbed during normal occupation and maintenance. Where refurbishment work will open up walls, lift finishes or remove building elements, a refurbishment and demolition asbestos survey is generally the more appropriate approach for the affected areas. The survey scope must reflect the works, not merely the age or appearance of the property.

Why a pre-refurbishment inspection was needed

The landlord initially considered proceeding with a general building inspection and asking the contractor to remain alert for suspect materials. That approach would have left too much to chance. Once workers begin lifting vinyl flooring, drilling through boards or stripping out a kitchen, a concealed material can be disturbed before it is recognised.

For this project, the proposed works included several higher-risk activities: removing old vinyl tiles and adhesive, accessing service risers, chasing walls for electrical cables and replacing soffit linings around pipework. These were precisely the areas where historic asbestos use could be present.

The survey was therefore commissioned before contractors were appointed for strip-out work. The objective was to inspect all areas due to be disturbed, identify suspect materials, arrange representative sampling where appropriate and provide clear recommendations that could be incorporated into the works plan.

Findings from the asbestos case study

The inspection identified a number of materials requiring attention. Not every suspect item contained asbestos, which is why sampling and accurate records were essential rather than assumptions based on visual appearance alone.

Laboratory analysis confirmed chrysotile asbestos in the vinyl floor tiles and associated bitumen adhesive in the kitchen and hallway. The materials were largely intact, but the planned removal of the finishes would create a foreseeable disturbance risk. Chrysotile was also identified in a textured coating to a small section of ceiling within a storage cupboard where new lighting was proposed.

More significantly, asbestos insulation board was identified to boxing around heating pipework within a service cupboard. This material was in fair condition but had small areas of damaged edge detail, likely caused by previous maintenance access. Because asbestos insulation board can release fibres more readily when disturbed, it required a more controlled removal approach than the floor tiles.

The survey also found cement-based panels to the underside of a communal external canopy. Although these panels were outside the flat and not part of the immediate internal works, they were noted because the landlord had proposed installing a new extractor duct through the adjacent wall. The recommendation was to revise the duct route so the cement panels would not need to be penetrated or disturbed.

The findings did not mean the refurbishment had to be abandoned. They changed how the work needed to be sequenced and delivered.

What the results meant in practice

The floor tiles and adhesive could not simply be lifted by the general refurbishment team. The method of removal needed to be determined by a competent contractor following a suitable risk assessment and plan of work. Depending on material condition, extent and removal method, licensing requirements and control measures can differ. A survey report should inform this decision, not replace the contractor’s legal planning responsibilities.

The asbestos insulation board was treated as the priority item. The area was isolated from other planned activity, and a suitably licensed asbestos removal contractor was engaged to remove it before electrical and heating works began. Following removal, the relevant clearance and certification process was completed before other trades returned to the cupboard.

For the textured coating, the landlord chose to retain the material and alter the lighting design rather than disturb the ceiling. This was a sensible cost and risk decision. Asbestos does not automatically need removing if it is in good condition, can be safely managed and will not be disturbed by planned works.

Protecting the budget and programme

The survey created an additional early cost, but it prevented a much more expensive problem later. Had the contractor started strip-out without the information, work could have stopped abruptly after the discovery of suspect floor tiles or board. The site may then have required isolation, assessment of potential contamination, revised quotations and delays while replacement contractors were arranged.

Instead, the landlord could obtain removal quotations before committing to the main refurbishment programme. The asbestos works were scheduled first, followed by electrical first-fix, plumbing and kitchen installation. This sequencing kept unrelated trades away from affected areas and reduced downtime.

The final refurbishment programme moved by just over a week rather than the several weeks that can result when asbestos is discovered mid-project. The landlord also avoided paying a general builder to wait on site while specialist works were arranged.

There was another financial benefit. The revised extractor route avoided unnecessary work near the external asbestos cement panels. In property projects, the lowest-risk option is often to design out disturbance where possible. Removal is not always the best answer, particularly where a material is sound and a minor design change can eliminate contact with it.

Lessons for buyers, landlords and developers

This asbestos case study demonstrates why asbestos planning should sit alongside the initial scope of works, not be left until the contractor arrives. Buildings constructed or refurbished before 2000 can contain asbestos in many locations, including floor finishes, textured coatings, pipe boxing, soffits, panels, lagging, roofing products and fire-protection materials. A property can look modern after repeated redecoration while older materials remain behind finishes.

The right survey depends on the property and the work proposed. A buyer considering a future renovation may need clear advice on likely asbestos risks before exchange or before setting a renovation budget. A landlord planning a kitchen replacement needs a survey that covers the kitchen, service areas and any finishes to be removed. A developer undertaking major alteration needs a far wider intrusive survey, potentially including concealed voids and structural elements.

Survey limitations should also be understood. Areas that are inaccessible, locked, unsafe or outside the agreed scope may not be inspected. A professional report should record these limitations clearly so that further investigation can be arranged before work reaches those locations. Certainty comes from an inspection that is properly matched to the planned disturbance, not from a generic statement that a property has been checked.

Turning survey information into action

A useful asbestos report should help the client decide what happens next. It should identify the material, location, extent, condition and likelihood of disturbance, then set out prioritised recommendations. For refurbishment projects, that information should be shared with the principal contractor and relevant trades before work begins, alongside any removal documentation and revised drawings.

Property owners should retain survey records and certificates after the works are complete. They may be needed for future maintenance, sale enquiries, insurance matters or further alterations. They also provide evidence that the work was planned responsibly rather than dealt with reactively.

For landlords and homeowners, the key message is straightforward: do not price refurbishment works on assumptions where asbestos may be present. A focused inspection provides the evidence needed to protect people, control costs and keep the programme moving. HICH LTD can help clients establish the right survey scope before refurbishment work turns a hidden material into an urgent site problem.

Enquire Now

Use the form below to get in touch to book a survey or to ask a question. Alternatively, you can call us on 0345 257 0858 (local rate)










    “Very responsive to emails and were the quickest company to give me a quote. Provided a professional and very detailed but clear report following my survey.”

    David Wotherspoon (Facebook Review)